Fervo's Contracted Revenue Climbs to $11.9B as Google Geothermal Plant Advances

Fervo said contracted revenue reached $11.9 billion in the third quarter, up from $7.2 billion three months earlier, as the geothermal developer moves ahead on a 396 megawatt plant for Google in Utah.

The figure was disclosed in the company's third-quarter earnings report, released Monday. The jump from $7.2 billion in the prior quarter comes as Fervo has been meeting deadlines on its project pipeline, according to the company.

The Google project, now called Cape Google 400, is slated for completion by the end of 2028. Co-founder and chief executive Tim Latimer said on a Monday earnings call that the plant will be grid connected, an arrangement that allows Google to draw power from the deal and sell it to other customers if the search giant is not yet ready to use it.

Both that project and Fervo's first commercial plant are located at Cape Station in Utah. Fervo connected its first 100 megawatt plant to the grid earlier this year. The site is now assessed as a resource capable of generating 8.4 gigawatts of electricity, roughly double the 4 gigawatts experts had previously told the company it could produce.

The orders are arriving as hyperscale technology companies search for large volumes of electricity to run AI data centers, a category of customer that has become a major driver of new power procurement.

Fervo is also targeting natural gas as it works to lower geothermal drilling costs at the Utah resource, according to the company.